India's vast coastline and unique topography offer significant potential for wind energy, a key renewable resource. However, its spatial distribution remains limited due to factors like inconsistent wind speeds and infrastructure challenges.

Q.7 Examine the potential of wind energy in India and explain the reasons for their limited spatial spread.

Model Answer:

Introduction

As of 2023, India has an installed wind power capacity of approximately 42.6 GW, making it the fourth-largest wind power producer globally, after China, the United States, and Germany.

Body

India has significant wind energy potential due to several factors

a) Geographical advantages:

  • Long coastline (over 7,600 km) providing offshore wind potential
  • Presence of mountain ranges and plateaus creating wind corridors

b) Renewable energy goals:

  • India aims to achieve 500 GW of renewable energy capacity by 2030
  • Wind energy is expected to play a crucial role in meeting this target. 

c) Current capacity and growth:

  • As of 2021, India's installed wind power capacity was around 40 GW
  • It ranks fourth globally in terms of cumulative wind power capacity. 

d) Technological advancements:

  • Improvements in turbine technology are making wind power more efficient and cost-effective
  • Potential for hybrid wind-solar projects to optimise land use and grid integration. 

Despite the significant potential, wind energy development in India has been concentrated in specific regions. 

Here are some reasons for this limited spatial spread - 

a) Geographical constraints

  • Most wind potential is concentrated in coastal and mountainous regions
  • Many interior regions have insufficient wind resources for large-scale projects

b) Land availability and acquisition issues

  • Wind farms require large tracts of land, which can be challenging to acquire in densely populated areas
  • Competing land uses (agriculture, forestry, urban development) limit available sites

c) Grid infrastructure limitations

  • Many high-potential wind sites are in remote areas with limited grid connectivity
  • Inadequate transmission infrastructure in some regions hinders wind farm development

d) Policy and regulatory challenges

  • Inconsistent policies across different states
  • Complex land acquisition and environmental clearance processes

e) Economic factors

  • High initial investment costs for wind projects
  • Limited financial incentives in some regions

f) Technical challenges

  • Need for specialised skills and equipment for installation and maintenance
  • Difficulty in transporting large turbine components to remote locations. 

Conclusion

By improving grid infrastructure, implementing consistent and supportive policies across all states and streamlining land acquisition and clearance processes India could potentially unlock more of its wind energy potential and achieve a wider spatial distribution of wind power projects across the country.